1) |
To install the distribution service, begin excavating at the curb stop installed by Easton Suburban Water
Authority. Excavation near the curb stop should be done only using hand tools. Caution: Contractors are
responsible for any damage to the services.
|
| |
2) |
The service lateral should be installed at a minimum depth of 48 inches below finished grade.
|
| |
3) |
Backfill the excavation to prevent damage or freezing of the service connection. Backfill material
should be free of large rock.
|
| |
4) |
If the curb stop will be located in a sidewalk, driveway or other paved area, contact the Authority at
least 48 hours before paving or pouring concrete. Easton Suburban Water Authority's Distribution
Department personnel will inspect the elevation of the curb box to verify access to the curb stop. You
are not permitted to pour any concrete or paving material until ESWA issues a final approval on the curb
box.
|