1) |
Contact the Engineering Department of Easton Suburban Water Authority at 610-258-7181, ext. 218 with the address
of the property. Easton Suburban Water Authority will determine the location of the closest water main. If an
extension is required, Easton Suburban Water Authority's Engineering Department will provide you with an estimate
of the cost involved to extend the line or install the service.
|
| |
2) |
In addition to any water main extension or installation fees, you will be required to pay a
tapping fee, which must be submitted with your application for service. The amount of the tapping
fee varies based on the size of the service you require. Our Engineering Department will be able
to assist you in determining the amount of your tapping fee.
|
| |
3) |
Your service installation will be scheduled upon receipt of your application form and tapping fee.
Under most circumstances, installation can be completed within 3 to 4 weeks.
|