Myrtle Avenue Area Water System Improvements:
Easton Suburban Water Authority has completed the water system portion
of a project to replace the cast iron water mains on Myrtle Avenue,
Cottage Street between Elizabeth Avenue and Myrtle Avenue, Farragut
Street between Myrtle Avenue and Nelson Avenue, Johnson Street between
Myrtle Avenue and Nelson Avenue, Nelson Avenue and Waverly Street
between Myrtle Avenue and Nelson Avenue. The 6" cast iron water mains
were replaced with new 8" ductile iron water mains and the service
laterals were transferred to the new water mains. The water system
work was completed in May of 2021 and permanent pavement restoration
will be performed in Summer of 2021.
Allen Street Water System Improvements:
Easton Suburban Water Authority started a project in May of 2021 to
replace the existing cast iron water main on Allen Street between Berks
Street and Pike Street in Palmer Township with a new 8” ductile iron
water main. The water system work was completed in May and permanent
pavement restoration will be included in Palmer Township’s Street
Improvement Project.
Lincoln Street Water System Improvements:
Easton Suburban Water Authority started a project on June 1, 2021 to
replace the existing 6" cast iron water main on Lincoln Street between
Seitz Street and Reynolds Street in the City of Easton with a new 8"
ductile iron water main. The water system work has been completed and
permanent pavement restoration will be performed in the Summer of 2021.
Fairview Avenue Water System Improvements:
Easton Suburban Water Authority started a project in June to replace
the existing 6" cast iron water main on Fairview Avenue west of 22nd
Street in Wilson Borough with a new 8" dductile iron water main. The
new water main has been installed and tested and the Authority is in
the process of transferring the water service laterals to the new water
main. Water system work should be completed in early July and
permanent pavement restoration will be completed in 2021.
2021 Bethlehem & Palmer Township Water System Improvements:
Easton Suburban Water Authority is in the construct phase of a project
to replace the existing cast iron water mains on Embur Terrace, Emerick
Terrace, Cibby Street, Circle Drive, King Avenue and Winfield Terrace
(between Embur and Chetwin) in Bethlehem and Palmer Townships with new
ductile iron water mains. Water system construction began on June 14,
2021 and should be completed by the end of July. Permanent pavement
restoration will be performed in the Fall of 2021.
Route 191 Water Main Improvements:
Easton Suburban Water Authority has completed the design phase of a
project to replace the existing water mains on Route 191 between
Newburg Road and Christian Springs Road in Lower Nazareth Township with
a new 12" ductile iron water main. The project will include the
connection of existing service laterals to the new water main and the
abandonment of the existing water mains on this portion of Route 191.
The project will be bid in the Summer of 2021, with construction
beginning in the Fall of 2021 and the project being completed in the
Spring of 2022.
Arndt Road & Bushkill Park Drive Water Main Installation:
Easton Suburban Water Authority has completed the design phase of a
project to install water main on Arndt Road between Bushkill Drive and
Bushkill Park Drive and Bushkill Park Drive between Friendly Tavern
Lane and Arndt Road in Forks Township. The project will be bid in the
Summer of 2021, with construction beginning in the Fall of 2021 and the
project being completed in the Spring of 2022.
Eldridge & Hermitage Avenues Water System Improvements:
Easton Suburban Water Authority is in the design phase of a project to
replace the existing cast iron water mains on Eldridge Avenue and
Hermitage Avenue in Palmer Township with new ductile iron water mains.
Design will be completed in 2021, with construction anticipated to be
performed in 2022.
Last Updated: 6/21/2021
|